Update Construction Progress Of Xindadong Textiles – Dung Quat On August 27, 2019

Update Construction Progress Of Xindadong Textiles – Dung Quat On August 27, 2019

TEXTILE FACTORY
– Installing formwork for cover of ditch along air conditioning room axis F / 14-20.
– Installing formwork for column, 3rd floor, axis 15-16A / H-G; 12-17 / A-B
– Installing formwork for spraying tank axis 12-17 / A-B
– Installation of reinforcement for floor beam on the 3rd floor, axis 18-20 / H-G
– Installing formwork into beam
– Installation of 
steel collar beam
– Building wall axis 22-23 / A-H; 21-17 / A-B

PREPARATION FACTORY FOR RAW MATERIAL

– Clean the foot of the column, pour sika grout for column foot
– Installation of reinforcement, formwork for the second floor of air conditioning room
– Installation of reinforcement, formwork  for column of the 2nd floor, axis L-M / 11-17
– Maintenance of concrete for floor beam L-M / 17-25; A-B / 16-25
– Installation of steel 
collar beam zone 5.6

– Building walls, pouring concrete for pillar of factory A-B / 1-25; K-M / 1-5

WASTEWATER TREATMENT AREA
– Tank No. 3: fabrication and installation of formwork, reinforcement for hanging wall, walking floor
– Tank No. 5: clean up materials, patching the hole of 
thread rod
– Tank No. 1: installation of scaffolding, beam formwork, floor for tank cover
– Tank No. 2: installation of reinforcement for floor cos 0.00

INFRASTRUCTURE OUTDOOR

– Remove the formwork into ditch, section M10-M11
– Combine the formwork into ditch M5-M6
– Pouring concrete for bottom of ditch M1-M2
– Leveling street D3, D1. 1 rolling to complete street D3

DORMITORY

– Installation of scaffolding on the roof
– Building wall on the 1st floor, axis 1-15 of the dormitory

WAREHOUSE
-Pause
GUARD’S HOUSE

– Leveling, compacting floor for guard’s house no.1

BOILER HOUSE
-Pause
PUMP ROOM FOR FIRE FIGHTING, WATER TANK

– Installation of reinforcement for the bottom of fire protection tank

ME/ ME SYSTEM
– Pressure test for filling pipe route 7. Digging and puting sanitary pipe for raw material factory
– Installation of putting recessed pipes for textile factory, pouring the foundation of street lamp pillars
– Fabricating water supply pipes for fire fighting, placing floor pipes for the textile factory

Pictures of construction:

Update Construction Progress Of Xindadong Textiles – Dung Quat On August 27, 2019
Update Construction Progress Of Xindadong Textiles – Dung Quat On August 27, 2019
Update Construction Progress Of Xindadong Textiles – Dung Quat On August 27, 2019
Update Construction Progress Of Xindadong Textiles – Dung Quat On August 27, 2019