Content of works:
TEXTILE FACTORY

  • Construction of ramp, repairing door axis 12-13 / A; H
  • membrane waterproofing axis 12-19 / G-H
  • Construction of patching and repairing air conditioning room No. 3, 4
    PREPARATION FACTORY FOR RAW MATERIAL
  • Build deck floor axis H-F / 20-25, complete air conditioning room
  • Installing scaffolding axis J-G / 7-12. Remove scaffolding axis C / 6-11
  • Construction of fireproof wall axis G / 1-4, K-J / 14-17
  • Putty axis K / 14-20, J-G / 13-5, M / 1-7, J-G / 1-5, C / 15-20, G / 5-9
  • Construction of doors, glass walls for the office area

WASTEWATER TREATMENT AREA – WATER TANK

  • Plastering wall outside the operation house
  • Installation of reinforcement, pouring concrete for floor of operation house
  • Waterproofing for tank wall
    WAREHOUSE
  • Installation of reinforcement for foundation axis A-C / 1-8
  • Cut settlement joints of foundation
  • Building walls on the first floor
  • Making wall by corrugated iron for warehouse
    BOILER HOUSE
  • Construction of wall axis BC / 6- 7
  • Plastering wall in house on axis BC / 6-7 and AB / 1-2
  • Making wall by corrugated iron for boiler house
    ME SYSTEM
  • Installation of highbay lights, sockets, construction of factory steam pipes, installing wc lights, installing light electric cables for raw material factory area.
  • Installing the light power cable, outdoor supply pipe
  • installing the light electric cable, install the textile factory socket.
  • Put the rainwater drainage outside the house.
  • Aligning lamps, equipment for dormitory
  • installing wire of street lights into the station.
  • Installation of textile factory lamps.
    FIRE PROTECTION
  • Connection of main pipes, branch pipes, nozzles, fire detectors, finished product warehouses, raw material factory, textile factory
  • Installing the pump for pump house of fire protection tank, fabricating pipe
    Pictures of construction
Update construction progress of Xindadong Textiles – Dung Quat on Dec 25, 2019
Update construction progress of Xindadong Textiles – Dung Quat on Dec 25, 2019
Update construction progress of Xindadong Textiles – Dung Quat on Dec 25, 2019
Update construction progress of Xindadong Textiles – Dung Quat on Dec 25, 2019