Update construction progress of Xindadong Textiles – Dung Quat on Dec 25, 2019

Content of works:
TEXTILE FACTORY
- Construction of ramp, repairing door axis 12-13 / A; H
- membrane waterproofing axis 12-19 / G-H
- Construction of patching and repairing air conditioning room No. 3, 4
PREPARATION FACTORY FOR RAW MATERIAL - Build deck floor axis H-F / 20-25, complete air conditioning room
- Installing scaffolding axis J-G / 7-12. Remove scaffolding axis C / 6-11
- Construction of fireproof wall axis G / 1-4, K-J / 14-17
- Putty axis K / 14-20, J-G / 13-5, M / 1-7, J-G / 1-5, C / 15-20, G / 5-9
- Construction of doors, glass walls for the office area
WASTEWATER TREATMENT AREA – WATER TANK
- Plastering wall outside the operation house
- Installation of reinforcement, pouring concrete for floor of operation house
- Waterproofing for tank wall
WAREHOUSE - Installation of reinforcement for foundation axis A-C / 1-8
- Cut settlement joints of foundation
- Building walls on the first floor
- Making wall by corrugated iron for warehouse
BOILER HOUSE - Construction of wall axis BC / 6- 7
- Plastering wall in house on axis BC / 6-7 and AB / 1-2
- Making wall by corrugated iron for boiler house
ME SYSTEM - Installation of highbay lights, sockets, construction of factory steam pipes, installing wc lights, installing light electric cables for raw material factory area.
- Installing the light power cable, outdoor supply pipe
- installing the light electric cable, install the textile factory socket.
- Put the rainwater drainage outside the house.
- Aligning lamps, equipment for dormitory
- installing wire of street lights into the station.
- Installation of textile factory lamps.
FIRE PROTECTION - Connection of main pipes, branch pipes, nozzles, fire detectors, finished product warehouses, raw material factory, textile factory
- Installing the pump for pump house of fire protection tank, fabricating pipe