Update Construction Progress Of Xindadong Textiles – Dung Quat On Oct 28, 2019

Update Construction Progress Of Xindadong Textiles – Dung Quat On Oct 28, 2019

Content of works has done:

TEXTILE FACTORY

– Building and plastering 2nd floor, axis 12-21 / A-B, building wall for flow room and drilling steel to wait room
– Installation of formwork
– Pouring concrete for foundation
– Plastering in the house on the first floor, air conditioning room axis 12-17 / G-H
– Putty ceiling, painting priming axis 12-17 / A-B, 12-17 / G-H
– Roofing: Seamlock tole, roof completion, gable V welding.

PREPARATION FACTORY FOR RAW MATERIAL

– Installation of reinforcement, concrete maintenance for the factory floor
– Installing HDPE drainage pipes in the factory floor.
– Installing the code of machine base No. 11; formwork, reinforcement for base no. 8
– Laminating the floor and tiling the room on the second floor, axis A-B / 1-25

– Putty on the walls, floor beams in the house on the 2nd floor, axis A-B / 1-9; M / 13-25; outside axis A / 9- 25. Paint priming and color outside factory axis A / 1-9
– Building and plastering wall, axis K-M / 5-11, K-G / 20, G / 1-15, A-B / 9-16, M / 1-5, A / 16-25
electric room
– Compacting stone for factory foundation
– Concrete maintenance for factory foundation
– Roofing: Roofing layer 2, screwing inox tole

WASTEWATER TREATMENT AREA

– Tank No. 2: fabrication and installation of formwork for wall phase 2
– Tank No. 7: Remove formwork of tank floor no. 7

INFRASTRUCTURE OUTDOOR

– Combine formwork into ditch
– Dredging ditches, leveling ground

DORMITORY

– Rolled foundation on the 2nd, 3rd, 4th floor, glazing seno on the 4th floor, tiling wall for 2nd floor
– Plastering 4th floor, attic, staircase
– Welding V, pouring concrete for open ditch
– Putty outside house, inside the house on the 3rd floor
– Painting to finish in house, 1st, 2nd floor;

BOILER HOUSE

– Absorbing water, defect the machine base
– Installing formwork for remaining small machine base

WAREHOUSE

Decking, laying loose purlin

MUD SEDIMENTATION TANK

Fabrication, installation of formwork, reinforcement for wall, column phase 2

GUARD’S HOUSE

– Building wall of guard’s house no. 1

ME

– Construction of compressed air, supply water under the wind ditch of the textile factory
– Installation of water supply pipes outside the finished product warehouse
– Installation of pneumatic pipes, light electricity for raw material factory
– Installing electric pipes, water supply and drainage, installing cables for the dormitory,
– Installation of street lights

PCCC/ FIRE PROTECTION

– Installation of water supply pipes for fire fighting, raw materials factory
– Installing signal cable outside the house, fabricating pipes

Illustrating pictures of construction

Update Construction Progress Of Xindadong Textiles – Dung Quat On Oct 28, 2019
Update Construction Progress Of Xindadong Textiles – Dung Quat On Oct 28, 2019
Update Construction Progress Of Xindadong Textiles – Dung Quat On Oct 28, 2019
Update Construction Progress Of Xindadong Textiles – Dung Quat On Oct 28, 2019