Update Construction Progress Of Xindadong Textiles – Dung Quat On Sep 06, 2019

TEXTILE FACTORY

• Building and plastering wall axis 22-23 / A-H, 17-21 / A-B
• Installing and combining formwork for floor beam axis 12-17 / H-G; A-B / 12-21 deck

PREPARATION FACTORY FOR RAW MATERIAL

• Installation of formwork  for machine base No. 6
• Installation of floor beam scaffolding on the 3rd floor axis K-M / 5-11
• Installation of collar beam zone 5, 6
• Building and plastering wall covering on the 2nd floor of axis A-B / 1-16; A-B / 14-25; K-M / 1-5

WASTEWATER TREATMENT AREA

• Tank No. 1: fabrication and installation of reinforcement, formwork of floor beam
• Tank No. 2: fabrication and installation of reinforcement, formwork of column D / 1-5
• Tank No. 3: fabrication and installation of reinforcement, formwork of hanging wall
• Tank No. 5: processing and installation of reinforcement, formwork for pedestrian corridor
• Tank No. 4: Clean up materials in the tank

INFRASTRUCTURE OUTDOOR

• Pour concrete road N4, rolling foundation of road D5, remove foundation of road D3, and rolling foundation of road D3

DORMITORY

  • Fabrication and installation of reinforcement, formwork, pour concrete for column
  • Plastering wall of axis 1-15, 1st floor

STOREHOUSE
     • Compacting, rolling ground, axis 9-15 / A-D

GUARD’S HOUSE

  • Pause

BOILER HOUSE

  • Pour concrete for lining of foundation

PUMP ROOM FOR FIRE FIGHTING, WATER TANK

  •  Installation of bottom formwork, fire protection tank wall

ME

  • Place recessed pipes for preparation factory
    • Installing dormitory’s water drainage pipes, installing 
    recessed pipes for the textile factory
    • installing 
    recessed pipes for preparation factory, installation of water supply pipes for preparation factory

Pictures of construction

Update Construction Progress Of Xindadong Textiles – Dung Quat On Sep 06, 2019
Update Construction Progress Of Xindadong Textiles – Dung Quat On Sep 06, 2019
Update Construction Progress Of Xindadong Textiles – Dung Quat On Sep 06, 2019
Update Construction Progress Of Xindadong Textiles – Dung Quat On Sep 06, 2019