Update Construction Progress Of Xindadong Textiles Project – Dung Quat On August 28, 2019

TEXTILE FACTORY

  • Clean up and return to the warehouse
  • Construction of wall, axis 22-23 / A-H, 17-21 / A-B
  • Fabrication and installation of reinforcement, formwork for floor beam cos + 6.90m
  • Installation of scaffolding for floor beam system Cos + 6.90m

PREPARATION FACTORY FOR RAW MATERIAL

  • Installation of formwork, reinforcement of floor beam, A-B axis / 16-25
  • Suck the machine base
  • Installation of reinforcement, formwork for column of second floor of  room
  • Fabrication and installation of formwork of column L-M / 17-25
  • Building wall surrounding the factory, A-B axis/ 1-25; K-M / 1-5

WASTEWATER TREATMENT AREA

  • Tank No. 1: fabrication and installation of reinforcement of  floor beam
  • Tank No. 2: fabrication and installation of reinforcement and formwork for column
  • Tank No. 3: removing formwork, maintenance of concrete of walls; fabrication and installation of reinforcement and formwork for pedestrian corridor
  • Tank No. 5: fabrication and installation of reinforcement and formwork for walking corridor, bracing
  • Tank No. 4: removing formwork, concrete maintenance of pedestrian corridor

INFRASTRUCTURE OUTDOOR

  • Pour concrete for Street D1

DORMITORY

  • Fabrication and installation of reinforced, formwork for floor beam
  • Construction of wall, axis 1-15, floor 1

WAREHOUSE

  1. TPause

GUARD’S HOUSE

  1. Pause

BOILER HOUSE

  1. Pause

FIRE FIGHTING PUMP ROOM, WATER TANK

  • Fabrication and installation of reinforced, formwork for tank bottom

ME SYSTEM

  • Put pipe for floor of preparation factory. Chiseling, putting pipe for socket, switch, 9-25 / AB, preparation factory
  • Chiseling, put pipe for socket, switch of textile factory, combine foundation of street lamp pillars
  • Fabricating pipe, installing pipe DN 125 for preparation factory

Pictures of construction

Update Construction Progress Of Xindadong Textiles Project – Dung Quat On August 28, 2019
Update Construction Progress Of Xindadong Textiles Project – Dung Quat On August 28, 2019
Update Construction Progress Of Xindadong Textiles Project – Dung Quat On August 28, 2019
Update Construction Progress Of Xindadong Textiles Project – Dung Quat On August 28, 2019