Update Construction Progress Of Xindadong Textiles Project – Dung Quat On August 28, 2019
TEXTILE FACTORY
- Clean up and return to the warehouse
- Construction of wall, axis 22-23 / A-H, 17-21 / A-B
- Fabrication and installation of reinforcement, formwork for floor beam cos + 6.90m
- Installation of scaffolding for floor beam system Cos + 6.90m
PREPARATION FACTORY FOR RAW MATERIAL
- Installation of formwork, reinforcement of floor beam, A-B axis / 16-25
- Suck the machine base
- Installation of reinforcement, formwork for column of second floor of room
- Fabrication and installation of formwork of column L-M / 17-25
- Building wall surrounding the factory, A-B axis/ 1-25; K-M / 1-5
WASTEWATER TREATMENT AREA
- Tank No. 1: fabrication and installation of reinforcement of floor beam
- Tank No. 2: fabrication and installation of reinforcement and formwork for column
- Tank No. 3: removing formwork, maintenance of concrete of walls; fabrication and installation of reinforcement and formwork for pedestrian corridor
- Tank No. 5: fabrication and installation of reinforcement and formwork for walking corridor, bracing
- Tank No. 4: removing formwork, concrete maintenance of pedestrian corridor
INFRASTRUCTURE OUTDOOR
- Pour concrete for Street D1
DORMITORY
- Fabrication and installation of reinforced, formwork for floor beam
- Construction of wall, axis 1-15, floor 1
WAREHOUSE
- TPause
GUARD’S HOUSE
- Pause
BOILER HOUSE
- Pause
FIRE FIGHTING PUMP ROOM, WATER TANK
- Fabrication and installation of reinforced, formwork for tank bottom
ME SYSTEM
- Put pipe for floor of preparation factory. Chiseling, putting pipe for socket, switch, 9-25 / AB, preparation factory
- Chiseling, put pipe for socket, switch of textile factory, combine foundation of street lamp pillars
- Fabricating pipe, installing pipe DN 125 for preparation factory