Update Construction Progress Of Xindadong Textiles Project – Dung Quat On Oct 04, 2019

Update Construction Progress Of Xindadong Textiles Project – Dung Quat On Oct 04, 2019

Xindadong construction progress is being carried out according to the plan:

TEXTILE FACTORY

– Install wind slot of ditch cover

– Installation of base steel.

– Building and plastering axis 12-21 / G-H; 12-23 / A-E; plastering electric room

– Putty matis for ceiling, wall of air-conditioning room, putty outside, axis 23

– Transportation and roofing

– Leveling, compacting stone foundation

PREPARATION FACTORY FOR RAW MATERIAL

– Fabrication and installation of reinforcement, formwork for ditch, axis D + 900; C + 1100

– Fabrication and installation of bottom formwork of machine base no. 9

– Plastering wall outside factory, axis A / 1-9, plastering inside the first floor, axis A-B / 22-23

– Building and plastering wall to finish, 2nd floor, axis A-B / 1-9; K-M / 5-11; L / 17-25; L / 5-11

– Installation of scaffolding A / 16-25

– Grinding ceiling on the 2 floor, axis A-B / 1-9

– Installing cover for wind ditch

– Transportation and roofing

WASTEWATER TREATMENT AREA

Tank No. 5: Clean and clean tank materials

Tank No. 1: Backfill soil, clean up tank

Tank No. 2: Fabrication and installation of formwork, reinforcement,  pour concrete for wall phase 1

INFRASTRUCTURE OUTDOOR

– Leveling, compacting and pouring concrete Street D5

DORMITORY

– Tidy up materials, Defect in the house (column, WC …)

– Outer plastering of 1st, 4th, axis 1-15 / A-D

– Construction of wall covering 3rd floor, axis 1,15 / C-D

BOILER HOUSE

– Fabrication and installation of reinforcement, formwork for pouring concrete of machine base No. 3

– Pouring concrete to lining of ground beam

WAREHOUSE OF FINISHED PRODUCT

Installing frame of steel structure

FIRE FIGHTING PUMP ROOM, WATER TANK

– Installation of reinforcement of wall phase 1 of sedimentation tanks

– Fabrication and installation of formwork system of cover of fire protection tank

– Backfill the bottom of the fire protection tank with soil

ME/ ME SYSTEM

– Construction of water supply pipes outside, installation of recessed pipes in the preparation factory

– Installing water supply pipe, compressed air under the ditch, drilling and draining the core of wind ditch of textile factory

– Installation cable for street lights outside house, installing recessed pipes and floor pipes for dormitory

– Installation of recessed pipes, floor pipes for textile factory

– Installation of signal cable pipe, water supply pipes for firefighting preparation factory

Pictures of construction

Update Construction Progress Of Xindadong Textiles Project – Dung Quat On Oct 04, 2019
Update Construction Progress Of Xindadong Textiles Project – Dung Quat On Oct 04, 2019
Update Construction Progress Of Xindadong Textiles Project – Dung Quat On Oct 04, 2019
Update Construction Progress Of Xindadong Textiles Project – Dung Quat On Oct 04, 2019