Updated progress of Mahang – Dung Quat project on September 27, 2019
Contents of construction work:
- Installing reinforcement, formwork for column of wall
- Digging foundation, pouring lining, reinforcement, formwork, pouring concrete for foundation of dyeing workshop, completed workshop, waste water treatment tank
- Leveling and Compacting land for workshop
- Building ditch