Update Construction Progress Of BW Project – Phase 3 On Jul 14, 2019
Content of works
* Factory C11,C12
- Concrete Maintenance of axis 2
- Digging foundation of axis 2
* Factory B11
- Excavation and transportation of foundation land B11, C4, C5
- Digging foundation of B axis and pouring concrete to lining
- Installation of reinforcement, board lining, and pouring concrete for foundation of A axis
* Temporary electrical phase 3
- Continue fabricating electrical cabinet
- Continue installing temporary Power Lines