Update Construction Progress Of BW Project – Phase 3 On Oct 06, 2019

Construction progress of BW Project – Phase 3

* Factory C11-C12

 1. Factory C11-C12: Installation of corrugated iron for roof and wall of the factory (55%)
Factory C11-C12: Plastering wall, axis A, factory area (90%)
3. Factory C11-C12: Pour concrete for dome (100%)
4. Factory C11-C12: Installation of board lining, reinforcement for stairs

* Factory B11

1. Factory B12: Installation of corrugated iron for roof, factory area (90%)
2. Factory B11: Plastering wall, axis 1, factory area (90%)
3. Factory B12: Building wall of office area (55%)
4. Factory B11: Pour concrete for dome (100%)
5. Factory B11: Installation of corrugated iron for roof and wall of the factory area
6. Factory B11: Installation of board lining, reinforcement for stairs

* Factory B12

1. Factory B12: Roofing corrugated iron, the factory area (20%)
2. Factory B12: Plastering wall, axis M, factory area (90%)
3. Factory B12: Building wall of office area (65%)
4. Factory B12: Pour concrete for dome (100%)
5. Factory B12: Installation of board lining, reinforcement
 for stairs

* Factory C4

1. Factory C4: Roofing corrugated iron, the factory area (100%)
2. Factory C4: Installation of corrugated iron for wall (20%)
3. Factory C4: Building wall of office area (55%)
4. Factory C4: Plastering wall, axis M axis, the factory area (90%)
5. Factory C4: Pour concrete for dome (100%)
6. Factory C4: Installation of board lining, reinforcement for stairs

* Factory C5

1. Factory C5: Completion of columns, collar beamridge beam, steel structure bracing (90%)
2. Factory C5: Plastering wall, axis K axis, factory area (90%)
3. Factory C5: Installation of board lining, reinforcement for dome
4. Factory C5: Building the wall of the office area

* Factory C6

1. Factory C6: Completion of columns, collar beam, ridge beam, steel structure bracing (90%)
2. Factory C6: Plastering wall, axis H, factory area (35%)
3. Factory C6: Installation of board lining, reinforcement, roof beam
4. Factory C6: Building the wall of the office area

Infrastructure

1. Infrastructure: Installation of culverts and manholes for factory C4 and B11
2. Infrastructure: Welding HDPE pipes, digging retaining walls, axis 13, factory C4

Fire protection

1. Fire protection: Fabricating branch pipes, factories C11, C12, B11
2. Fire protection: Installing pipe DN 150, factories B11, C5
3. Fire protection: Fabricating DN 150 pipe, factory C6

* MEP

1. MEP: Construction of sanitary water supply pipes C4, C5, B11, B12
2. MEP: Construction of rainwater pipes, axis H, factory C11, C12

Illustrating pictures of construction

Update Construction Progress Of BW Project – Phase 3 On Oct 06, 2019
Update Construction Progress Of BW Project – Phase 3 On Oct 06, 2019
Update Construction Progress Of BW Project – Phase 3 On Oct 06, 2019
Update Construction Progress Of BW Project – Phase 3 On Oct 06, 2019

GOLDEN LOTUS CONSTRUCTION JSC .,