Update Construction Progress Of Perennial Cable Project – Phase 3 On May 18, 2020

Construction progress of Perennial Cable Project – Phase 3
– Fabrication of formwork for beam bottom, iron and steel, column of roof X1-8 / Y1-5 axis, factory E
– Concrete grinding for floor beam, 2nd floor X1-8 / Y1-5 axis, factory E
– Transporting scrap boards to 3rd floor of Factory E
– Installing reinforcement for column of 2nd floor, office area of factory
– Building auxiliary wall
– Combine formwork into ditch, ditch route A21-A22
– Installing reinforcement for ditch route A4 – A4-1
– Pour concrete for bottom of ditch, ditch route A4 – A4-1