Update Construction Progress Of Xindadong Textiles – Dung Quat On Sep 17, 2019
Construction works:
TEXTILE FACTORY
– Aligning the beam formwork, mounting beam steel + 9.9m axis 12-14 / H-G
– Building and plastering axis 12-21 / G-H, 23 / E-H; 12-21 / A-B; 22-23 / A-D
– Fabrication of floor reinforcement 1m
– Concrete grinding for floor beam, axis 22-23 / A-E
PREPARATION FACTORY FOR RAW MATERIAL
– Cleaning formwork of floor beam axis A-B / 16-25
– Installation of formwork for base machine No. 6
– Installation of formwork, reinforced for floor beam on the 3rd floor, axis K-M / 5-11 axis
– Building and plastering wall axis G / 1-5; G / 1-14; B / 1-13; A-B / 1-25; L / 11-17
– Grinding beams for column, axis B
– Installing scaffolding covering axis B / 9-16
WASTEWATER TREATMENT AREA
– Tank No. 1: Remove formwork for concrete maintenance of floor beams
– Tank No. 2: Fabrication and Installation of reinforcement, formwork for floor, wall
– Tank number 3: Cleaning materials
– Tank No. 5: Grinding and finishing concrete surface
– Tank No. 4: Grinding and finishing concrete surface
INFRASTRUCTURE OUTDOOR
– Fabrication and Installation of reinforcement, formwork for wastewater manholes PA7,8,9,10.
– Rolling, compact stone foundation street D5.
DORMITORY
– Building and plastering on the 2nd floor
– Fabrication and Installation of reinforcement, formwork for stairs on the 2-3 floor
WAREHOUSE
pause
GUARD’S HOUSE
– Fabrication and Installation of formwork of floor beams for guard’s house No. 1
BOILER HOUSE
Remove formwork of pedestal of Boiler House
FIRE FIGHTING PUMP ROOM, WATER TANK
– Fabricating formwork for mud sedimentation tanks, installing reinforcement for the bottom of mud sedimentation tanks
– Fabrication and installation of formwork and reinforcement for fire protection tank wall
GARAGE
Pause
ME
– Construction of water supply pipe for the textile factory, chiseling recessed pipes for preparation factory, Construction of water supply pipe for preparation factory, chiseling textile factory , chiseling to
the water supply and drainage pipes of the dormitory, put pillar for street lights.
– Construction of water supply and drainage, floor electric pipes of the dormitory, construction of pipes for wind ditches of textile factory
– Installing the primer wire for dormitory, install pipes inside and outside the preparation factory, pipe 50 textile factory.
Pictures of construction: