Update Construction Progress Of Xindadong Textiles Project – Dung Quat On Sep 22, 2019

Works has been done:

TEXTILE FACTORY

– Fabrication and installation of formwork, reinforcement for electric floor 1m
– Building and plastering 1st ,2nd floor, axis 12-21 / G-H; 12-17 / A-E; 22-23 / A-D
– Concrete grinding for floor beam, axis 22-23 / A-E

PREPARATION FACTORY FOR RAW MATERIAL

– Installation of formwork for base machine No. 6.
– Installation of formwork for ditch, HDPN drainage pipe
– Building and plastering wall on the 1st,2nd floor, axis A-B / 9-25, G / 1-14; L / 5-17
– Grinding floor beams indoor, axis A-B / 1-9
– Fabrication and installation for corrugated iron of roof axis G-K / 1-9

WASTEWATER TREATMENT AREA

– Tank No. 1: remove formwork, concrete maintenance for floor beams

– Tank No. 2: fabrication and installation for column formwork and reinforcement

– Tank number 3, 5: Grinding concrete surface

– Tank No. 7: fabrication and installation for formwork and reinforcement for foundation

INFRASTRUCTURE OUTDOOR

Remove road-bed of street N6
Digging ditch M11-M12, combine formwork into ditch M11-M12

DORMITORY
– Building and plastering on the 2nd,3rd floor
– Fabrication and installation of formwork, reinforcement, stairs for 3rd, 4th floors

WAREHOUSE

pause

GUARD’S HOUSE

pause

BOILER HOUSE

pause

FIRE FIGHTING PUMP ROOM, WATER TANK

– Fabricating formwork for bottom of sedimentation tanks, installing reinforcement for the sedimentation tank wall

– Fabricating reinforcement for cover of fire protection tank

ME SYSTEM

– Installation of rack in wind ditch of textile factory, installation of water supply pipes outside factory, installation recessed pipes, drilling and dropping Thread Rod on roof of factory 

– Construction of recessed pipes, water supply and drainage of the dormitory, combine foundation for street lamps

– Installation of water supply pipes for fire fighting inside and outside factory, install fire alarm cable for the dormitory

Pictures of construction

Update Construction Progress Of Xindadong Textiles Project – Dung Quat On Sep 22, 2019
Update Construction Progress Of Xindadong Textiles Project – Dung Quat On Sep 22, 2019
Update Construction Progress Of Xindadong Textiles Project – Dung Quat On Sep 22, 2019
Update Construction Progress Of Xindadong Textiles Project – Dung Quat On Sep 22, 2019

GOLDEN LOTUS CONSTRUCTION JSC .,