Update Construction Progress Of Xindadong Textiles Project – Dung Quat On Sep 22, 2019
Works has been done:
TEXTILE FACTORY
– Fabrication and installation of formwork, reinforcement for electric floor 1m
– Building and plastering 1st ,2nd floor, axis 12-21 / G-H; 12-17 / A-E; 22-23 / A-D
– Concrete grinding for floor beam, axis 22-23 / A-E
PREPARATION FACTORY FOR RAW MATERIAL
– Installation of formwork for base machine No. 6.
– Installation of formwork for ditch, HDPN drainage pipe
– Building and plastering wall on the 1st,2nd floor, axis A-B / 9-25, G / 1-14; L / 5-17
– Grinding floor beams indoor, axis A-B / 1-9
– Fabrication and installation for corrugated iron of roof axis G-K / 1-9
WASTEWATER TREATMENT AREA
– Tank No. 1: remove formwork, concrete maintenance for floor beams
– Tank No. 2: fabrication and installation for column formwork and reinforcement
– Tank number 3, 5: Grinding concrete surface
– Tank No. 7: fabrication and installation for formwork and reinforcement for foundation
INFRASTRUCTURE OUTDOOR
Remove road-bed of street N6
Digging ditch M11-M12, combine formwork into ditch M11-M12
DORMITORY
– Building and plastering on the 2nd,3rd floor
– Fabrication and installation of formwork, reinforcement, stairs for 3rd, 4th floors
WAREHOUSE
pause
GUARD’S HOUSE
pause
BOILER HOUSE
pause
FIRE FIGHTING PUMP ROOM, WATER TANK
– Fabricating formwork for bottom of sedimentation tanks, installing reinforcement for the sedimentation tank wall
– Fabricating reinforcement for cover of fire protection tank
ME SYSTEM
– Installation of rack in wind ditch of textile factory, installation of water supply pipes outside factory, installation recessed pipes, drilling and dropping Thread Rod on roof of factory
– Construction of recessed pipes, water supply and drainage of the dormitory, combine foundation for street lamps
– Installation of water supply pipes for fire fighting inside and outside factory, install fire alarm cable for the dormitory